  "schema_version": 1,
  "updated": "2026-09-22",
  "source": "TxDOT Project Tracker (apps3.txdot.gov/apps-cq/project_tracker), Texas Transportation Commission award list Oct. 31, 2024, Crockett City Council records. Figures are TxDOT construction estimates or contract awards as listed on the date above.",
  "projects": [
    {
      "csj": "1854-01-051",
      "route": "Loop 304",
      "what": "Resurface (overlay) the loop",
      "limits": "From just west of SH 21 around to just east of SH 19 — the whole loop except the southwest quadrant",
      "cost_usd": 13181850,
      "cost_note": "contract award",
      "let": "2024-10",
      "start": "2025-02-24",
      "finish": "2026-09-27 (estimated)",
      "status": "Under construction — about 62% complete as of Sept. 2026",
      "contact": "Jesse Sisco, P.E., TxDOT Lufkin Area Office",
      "in_city": true
    },
    {
      "csj": "—",
      "route": "Loop 304 (northwest)",
      "what": "Replace the northwest Loop 304 overpass near US 287 / SH 19 north",
      "limits": "Overpass only",
      "cost_usd": null,
      "cost_note": "not yet published",
      "let": "not yet scheduled",
      "start": "",
      "finish": "6–12 months once started",
      "status": "Planned — TxDOT says the structure is at end of life; demolish and rebuild in place; traffic to be diverted through town or around the south side of the loop. Council letter of support March 16, 2026.",
      "contact": "TxDOT Lufkin District",
      "in_city": true
    },
    {
      "csj": "0109-04-030",
      "route": "BU 287 (was US 287)",
      "what": "Overlay",
      "limits": "Loop 304 (north) to the Crockett town square — N. 4th St",
      "cost_usd": 1006019,
      "cost_note": "estimate",
      "let": "2027-04",
      "start": "",
      "finish": "",
      "status": "Programmed (UTP Category 1)",
      "contact": "Matt Brazil, P.E.",
      "in_city": true
    },
    {
      "csj": "0340-01-042",
      "route": "BU 287 (was US 287)",
      "what": "Overlay",
      "limits": "Crockett town square to Loop 304 (south) — S. 5th St / E. Bowie Ave",
      "cost_usd": 1010926,
      "cost_note": "estimate",
      "let": "2027-04",
      "start": "",
      "finish": "",
      "status": "Programmed (UTP Category 1)",
      "contact": "Matt Brazil, P.E.",
      "in_city": true
    },
    {
      "csj": "0109-05-045",
      "route": "BS 19 (was SH 19)",
      "what": "Overlay",
      "limits": "Crockett town square to Loop 304 — S. 4th St",
      "cost_usd": 1100000,
      "cost_note": "estimate",
      "let": "2027-04",
      "start": "",
      "finish": "",
      "status": "Programmed (UTP Category 1)",
      "contact": "Matt Brazil, P.E.",
      "in_city": true
    },
    {
      "csj": "0118-01-021",
      "route": "BS 21 (was SH 21)",
      "what": "Overlay",
      "limits": "Crockett town square to Loop 304 — E. Houston Ave",
      "cost_usd": 1020741,
      "cost_note": "estimate",
      "let": "2027-04",
      "start": "",
      "finish": "",
      "status": "Programmed (UTP Category 1)",
      "contact": "Matt Brazil, P.E.",
      "in_city": true
    },
    {
      "csj": "0336-01-067",
      "route": "BS 7 (was SH 7)",
      "what": "Overlay",
      "limits": "Crockett town square to Loop 304 — E. Goliad Ave",
      "cost_usd": 756153,
      "cost_note": "estimate",
      "let": "2027-04",
      "start": "",
      "finish": "",
      "status": "Programmed (UTP Category 11, district discretionary)",
      "contact": "Matt Brazil, P.E.",
      "in_city": true
    },
    {
      "csj": "1854-01-054",
      "route": "Loop 304 (southwest)",
      "what": "Seal coat",
      "limits": "SH 19 south to SH 7 west / SH 21 west — the southwest quadrant",
      "cost_usd": 216445,
      "cost_note": "estimate",
      "let": "2027-11",
      "start": "",
      "finish": "",
      "status": "Programmed (UTP Category 1)",
      "contact": "Matt Brazil, P.E.",
      "in_city": true
    },
    {
      "csj": "1854-01-050",
      "route": "Loop 304",
      "what": "Safety improvement",
      "limits": "0.5 mile north of SH 7 to SH 7",
      "cost_usd": 21595,
      "cost_note": "award",
      "let": "2024",
      "start": "2025-01-18",
      "finish": "2025-10-14",
      "status": "Complete",
      "contact": "Jeremy King, P.E.",
      "in_city": true
    },
    {
      "csj": "0109-05-043",
      "route": "SH 19",
      "what": "Resurface",
      "limits": "Loop 304 south 5.5 miles",
      "cost_usd": 3020000,
      "cost_note": "award",
      "let": "2024-10",
      "start": "",
      "finish": "",
      "status": "Let Oct. 2024",
      "contact": "Jesse Sisco, P.E.",
      "in_city": false
    },
    {
      "csj": "0187-503-023",
      "route": "FM 2110",
      "what": "Restoration",
      "limits": "SH 19 to 4 miles south of Loop 304",
      "cost_usd": 5541667,
      "cost_note": "estimate",
      "let": "2026-06",
      "start": "",
      "finish": "",
      "status": "Let June 2026; a second phase (0187-503-024, about $5.1M) is set for June 2027",
      "contact": "TxDOT Lufkin District",
      "in_city": false
    },
    {
      "csj": "2068-01-006",
      "route": "FM 2076",
      "what": "Restoration and widening of the pavement to 26 ft",
      "limits": "End of pavement to FM 229",
      "cost_usd": 5200000,
      "cost_note": "Project Tracker estimate; the district newsletter listed $11.4M",
      "let": "2025-08",
      "start": "",
      "finish": "",
      "status": "Let Aug. 2025",
      "contact": "TxDOT Lufkin District",
      "in_city": false
    },
    {
      "csj": "0340-04-032",
      "route": "FM 229",
      "what": "Resurface",
      "limits": "FM 2544 to SH 7",
      "cost_usd": 539053,
      "cost_note": "estimate",
      "let": "2025-11",
      "start": "",
      "finish": "",
      "status": "Programmed",
      "contact": "TxDOT Lufkin District",
      "in_city": false
    }
  ]
}